Building Approvals and Construction Finance: Reading the ABS Data Before You Build
ADS Team
Author
November 26, 2026
about 15 hours ago
9
views

In short: The ABS publishes two releases worth reading before you arrange construction finance: Building Approvals, monthly, which counts permits issued, and Building Activity, quarterly, which counts work started, under way and finished. Read the trend series for direction and the seasonally adjusted series for the latest month, and compare the pipeline with completions to judge how stretched builders are. Lenders read the same data when they assess your builder, your budget and your timetable.
Key takeaways
- The ABS defines a building approval as the official permit that allows construction to begin; it is a step before work starts, not a start.
- In August 2026, seasonally adjusted total dwelling units in building approvals fell 6.1% to 16,953, while the trend fell 0.8% to 18,202.
- Apartments and other attached dwellings swing far more month to month than houses; read their trend, not one month.
- Building Activity for the June quarter 2026 showed 248,733 dwellings under construction (original terms), the pipeline builders are working through.
- Lenders assess the builder, the contract and the contingency more closely when pipelines are full and costs are rising.
- Progress draws mean you pay interest only on what has been drawn; the timing of draws shapes the interest bill.
What do the ABS building approvals figures measure?
The ABS says a building approval is the official permit that allows construction to begin. Its monthly release counts these permits, mainly from local councils and other permit-issuing or certifying authorities, and reports the number of dwelling units and the value of residential and non-residential building. The scope covers new buildings, alterations and additions, non-structural renovation, installation of integral fixtures and full demolitions of existing dwellings.
The August 2026 Building Approvals release, published on 30 September 2026, reported:
| Series, August 2026 | Seasonally adjusted | Monthly change | Trend | Monthly change |
|---|---|---|---|---|
| Total dwelling units | 16,953 | -6.1% | 18,202 | -0.8% |
| Private sector houses | 10,885 | +3.7% | 10,749 | +0.5% |
| Private sector dwellings excluding houses | 5,674 | -21.2% | 7,105 | -2.6% |
| Value of non-residential building | $5.53 billion | -44.8% | $9.56 billion | +2.0% |
The September 2026 issue is due in early November 2026, so check the ABS Building Approvals series page for the latest month before you quote any of these.
Trend or seasonally adjusted: which should you read?
Both, for different questions.
- Seasonally adjusted figures remove regular calendar patterns, such as the summer holiday dip, but keep irregular moves. They tell you what happened this month.
- Trend figures smooth out the irregular moves as well, so they show direction. The latest trend points are revised as new months arrive.
August 2026 shows why the difference matters. Seasonally adjusted, private sector dwellings excluding houses fell 21.2% in a month; the trend fell 2.6%. Non-residential building value fell 44.8% seasonally adjusted, yet its trend rose 2.0%. A few large apartment or commercial projects being permitted in one month and not the next can swing the seasonally adjusted figure by that much without any change in the underlying market.
A practical rule: use the trend to judge whether activity in your segment is rising or falling, and the seasonally adjusted figure to see whether the latest month surprised. For houses, which come in large numbers of small projects, the two series sit closer together: in August 2026, 10,885 seasonally adjusted against a trend of 10,749.
What does the Building Activity release add?
Building approvals count permits. The quarterly Building Activity release counts what happens next: dwellings commenced, under construction and completed, the value of work done and the work still in the pipeline. Its scope is building work valued above $10,000 that has a building approval.
The June quarter 2026 Building Activity release, published on 7 October 2026, reported:
| June quarter 2026 | Figure | Change on March quarter |
|---|---|---|
| Dwelling commencements, seasonally adjusted | 52,201 | +7.0% |
| Dwelling commencements, trend | 51,421 | -0.2% |
| Dwelling completions, seasonally adjusted | 47,168 | +5.8% |
| Dwellings under construction, original | 248,733 (including 95,447 new houses) | - |
| Value of total building work done, seasonally adjusted, chain volume | $45.8 billion | +1.1% |
The ABS notes these estimates rest on a response rate of about 85%, lower than usual, and will be revised. For an earlier read each quarter, the Construction Work Done preliminary release gives the value of building and engineering work before Building Activity is published. For costs, the ABS Producer Price Indexes include building and house construction output prices; a new issue is due at the end of October 2026.
How do you read the pipeline from permit to completion?
Think of the data as a pipe. Building approvals are what enters at the top; commencements are work that actually starts; dwellings under construction are what is inside the pipe; completions are what comes out the bottom.
- Not every permit becomes a start. Projects are delayed, redesigned or abandoned, especially apartments that need presales or finance.
- The lag varies. A detached house may start soon after its permit; a large apartment project can take much longer.
- A large pipeline with slower completions suggests builders and trades are stretched. In the June quarter 2026, seasonally adjusted commencements (52,201) ran ahead of completions (47,168), so on those figures more work entered the pipeline than left it.
For someone about to build, a stretched pipeline matters more than the national total. It can mean longer build times, less negotiating room on price and more risk that a builder takes on more than it can deliver.
What does the data tell lenders about builders and appetite?
Lenders do not fund statistics; they fund your project. But the same data shapes how closely they look at it. When pipelines are full and construction prices are rising, lenders focus on:
| What the lender checks | Why it matters more in a stretched market |
|---|---|
| The builder's licence, insurance and financial position | A builder carrying too much work is a completion risk |
| Fixed-price contract versus cost-plus | Cost-plus contracts pass price rises to you, and the loan may not cover them |
| Contingency in the budget | Variations and escalation have to be funded somewhere |
| Progress payment schedule | Draws must match work done, verified by the lender's valuer or quantity surveyor |
| Build timetable | Longer builds mean more interest before the loan converts or is repaid |
Our guide to construction loans and how progress payments work covers the draw process, and construction and development finance covers larger projects. ASIC's Moneysmart glossary describes a construction loan as a type of home loan for people building their own home; larger projects use the same staged-draw structure.
Worked example: what draws and escalation do to the budget
For illustration only. A borrower owns the land and signs a $900,000 contract to build. The loan is interest-only during construction at an illustrative 7.5% (an example, not an offer), with draws paid at each stage and the build finishing in month 11.
| Stage | Share of contract | Draw | Month drawn | Months of interest to month 11 |
|---|---|---|---|---|
| Deposit | 5% | $45,000 | 0 | 11 |
| Base | 15% | $135,000 | 2 | 9 |
| Frame | 20% | $180,000 | 4 | 7 |
| Lock-up | 20% | $180,000 | 6 | 5 |
| Fixing | 25% | $225,000 | 8 | 3 |
| Completion | 15% | $135,000 | 10 | 1 |
The stage percentages are an illustration; real schedules depend on the contract and on state building laws. Interest is each draw times the months it is outstanding times 7.5% / 12. The draw-months add up to 4,680,000 ($45,000 x 11 + $135,000 x 9 + $180,000 x 7 + $180,000 x 5 + $225,000 x 3 + $135,000 x 1), so interest during the build is 4,680,000 x 0.625% = $29,250. If the full $900,000 had been drawn on day one, 11 months of interest would be $61,875.
Now add escalation. On a cost-plus contract, a 6% rise in costs on the 80% of work still to do after the base stage ($720,000) adds $43,200, nearly half of a 10% contingency of $90,000. A two-month delay before completion adds roughly another $11,250 of interest on the fully drawn $900,000 ($900,000 x 0.625% x 2). The construction progress draw calculator runs the same sums on your schedule.
How do banks, non-banks and private lenders differ on construction loans?
The market data affects lenders unevenly, because they fund construction in different ways. The table is a general guide only; individual lenders differ and their policies change.
| Banks | Non-bank lenders | Private lenders | |
|---|---|---|---|
| Typical construction loans | Owner-occupier and investor builds, smaller multi-unit projects | Builds that sit outside bank policy, including some owner-builders | Short-term funding where flexibility matters more than price |
| What they assess hardest | Serviceability, fixed-price contract, builder credentials | Security value, builder and exit | Security value and exit |
| Contingency expectations | Often want a contingency or evidence of extra funds | Usually want a contingency | Often build fees and interest into the loan |
| Response to a stretched market | Tighter on builders and cost-plus contracts | Pricing rises before appetite falls | Pricing reflects the risk directly |
Whichever lender you use, a valuation on an "as if complete" basis, a fixed-price contract with a licensed and insured builder, and a budget with a real contingency are what make construction finance work when builders are busy. The data tells you how busy they are.
How should you use the data before you build?
- Look at your segment. Houses and apartments behave differently; read the series for the type you are building.
- Look at your area. The ABS publishes small-area data for Building Approvals; local activity matters more than the national figure.
- Read the trend for direction and the seasonally adjusted figure for the latest surprise.
- Compare commencements with completions to judge how stretched builders are.
- Ask your builder about their pipeline: how many jobs they have under way, and their expected start and finish dates for yours.
- Budget a contingency and prefer a fixed-price contract where you can.
- Line up construction loans before you sign, with finance conditional on the contract and plans.
When you are ready, post one construction loan request on ADS and 200+ verified lenders and brokers can ask about it.
Frequently asked questions
What is the difference between building approvals and building commencements?
A building approval is the permit that allows construction to begin; a commencement is when work actually starts on site. The ABS counts building approvals monthly in its Building Approvals release and commencements quarterly in Building Activity. Not every permitted project starts, and the gap between the two can be months or longer.
Should I use trend or seasonally adjusted building approvals?
Use trend to judge direction, because it smooths out large one-off projects, and seasonally adjusted to see what happened in the latest month. Apartment and non-residential figures can swing sharply month to month; in August 2026 the seasonally adjusted value of non-residential building fell 44.8% while its trend rose 2.0%.
How often does the ABS release building data?
Building Approvals is monthly. Building Activity, which covers commencements, completions and dwellings under construction, is quarterly, and Construction Work Done gives a preliminary quarterly read before it. Release dates are on each ABS series page; the September 2026 Building Approvals issue is due in early November 2026.
Do lenders look at building approvals data?
They watch the market data, but they assess your project on its own terms: the builder, the contract, the budget and contingency, the valuation and your ability to repay. A stretched market tends to make lenders look harder at builder capacity, fixed-price contracts and contingency, because those are where construction projects go wrong.
How do progress draws reduce construction loan interest?
You pay interest only on what has been drawn, and each stage is drawn as work is completed. In the illustrative example above, staged draws on a $900,000 contract cost about $29,250 in interest over an 11-month build, against $61,875 if the full amount were drawn at the start.
Related reading
- Construction Loans: How Progress Payments Work
- Construction and Development Finance
- LVR and Equity: Worked Calculations
Sources
- Building Approvals, Australia, August 2026 — Australian Bureau of Statistics
- Building Approvals, Australia (series page) — Australian Bureau of Statistics
- Building Activity, Australia, June quarter 2026 — Australian Bureau of Statistics
- Construction Work Done, Australia, Preliminary — Australian Bureau of Statistics
- Producer Price Indexes, Australia — Australian Bureau of Statistics
- Construction loan (glossary) — ASIC Moneysmart
Information current as at 24 October 2026.
General advice warning: This article contains general information only. It does not take into account your objectives, financial situation or needs, and it is not personal credit or financial advice. Consider whether it is appropriate for you and seek advice from a licensed credit representative before acting.
Any interest rate shown is an example only and is not an offer of credit. Where a rate is quoted, the applicable comparison rate is available from the relevant lender and should be considered alongside it.
Tags
Related Posts

Late Payments and Small Business Cash Flow: What Borrowers Can Do About It
Late payments turn sales you have already made into cash you cannot use, and a small business pays for the gap with its own overdraft, its suppliers' patience or the owner's savings. You can shorte...

Business Credit Indicators: How to Read the RBA and ABS Lending Data
Two official series tell you most of what is happening to business credit in Australia. The RBA's monthly Financial Aggregates show how much the total stock of lending to businesses is growing; its...

How a Cash Rate Rise Flows Through to Business Loan Repayments
A cash rate rise reaches business loan repayments through the lender's funding costs. Bank bill rates move, the lender reprices its variable business rates, and repayments change at the next reset....